PROJECTS

Infrastructure Projects

Delivery cases across networks, security, identity, servers, virtualization, data protection, migration and managed support, with scope, implementation controls, validation and handover.

Infrastructure delivery, shown through real project work.

18 delivery cases spanning network and security, identity and access, server and virtualization platforms, data protection, migrations, and managed infrastructure support.

Filter by capability
Pharmaceutical company in Hangzhou | VSAX backup server rollout
HangzhouPharmaceutical

Hangzhou pharma | VSAX backup rollout

An independent backup server was introduced to move critical data protection away from ad-hoc operations. The project covered backup scope, retention, job sequencing, restore validation and handover, so a green job status was not treated as the only acceptance criterion.

View project details →
Pharmaceutical company in Taizhou | Rose HA and SQL Server rollout
TaizhouPharmaceutical

Taizhou pharma | Rose HA + SQL Server

A two-node SQL Server environment was delivered with Rose HA. Database services, storage, addresses, dependencies and application validation were managed as one change plan rather than separate installation tasks.

View project details →
Manufacturing company in Yuhang, Hangzhou | IP-Guard rollout for about 200 endpoints
Hangzhou YuhangManufacturing

Yuhang manufacturer | IP-Guard for ~200 endpoints

Five IP-Guard modules were introduced across about 200 endpoints. Department and endpoint grouping, pilot policy design and phased deployment were used to avoid pushing one restrictive policy to production and office users at the same time.

View project details →
IoT company in Yuhang, Hangzhou | integrated firewall, core network, AD, backup and VDI rollout
Hangzhou YuhangIoT

Yuhang IoT | Network, AD, backup & VDI rollout

This was a multi-workstream infrastructure delivery in which firewall policy, the core network, AD, backup and internal virtual desktops depended on one another. The project therefore established the architecture and dependency baseline first, then delivered in controlled stages.

View project details →
Healthcare company in Fuyang, Hangzhou | 20 TB NAS backup planning and rollout
Hangzhou FuyangHealthcare

Fuyang healthcare | 20 TB NAS backup platform

A roughly 20 TB NAS environment was planned and brought online for data protection. Capacity, directory layout, permissions, network transfer and restore requirements were considered together so the NAS would remain maintainable after the initial data load.

View project details →
Real-estate group in Zhuji | virtualization, backup, network security and application operations
ZhujiReal estate

Zhuji real estate | Virtualization & application operations

Managed support covered virtualization, backup, network security and five business systems. The focus was to create an environment another engineer could understand: assets, dependencies, recurring checks, change records and risk items were progressively turned into an operating baseline.

View project details →
IoT company in Shenzhen | Windows Server 2025 AD and file sharing rollout
ShenzhenIoT

Shenzhen IoT | Windows Server 2025 AD & file services

A new Windows Server 2025 AD environment and enterprise file-sharing structure were delivered together. OU design, DNS, Group Policy, security groups and NTFS/share permissions were planned as one access model rather than adding permissions after the shares were created.

View project details →
Specialist hospital in Henan Province | network remediation, health-insurance / government dedicated links and backup
HenanHealthcare

Henan hospital | Network remediation & dedicated-link integration

The hospital environment combined internal services with health-insurance and government dedicated links. Network remediation, routing, access control, cross-party link testing and backup were managed in one change plan, with business-port validation rather than relying on ping alone.

View project details →
Trading company in Shanghai | Windows Server 2003 AD rebuild and policy recovery
ShanghaiTrading

Shanghai trading | Windows Server 2003 AD rebuild

A legacy Windows Server 2003 domain had accumulated years of identity, DNS, permission and policy dependencies. The work started with read-only evidence collection, then rebuilt and restored the required relationships in stages rather than making repeated changes directly on an unknown legacy state.

View project details →
Port operator in Foshan | Windows Server 2022 dual-DC AD rollout
Foshan, GuangdongPort operations

Foshan port | Windows Server 2022 dual-DC AD

A two-domain-controller Windows Server 2022 environment was planned and deployed with emphasis on replication, DNS, time, FSMO roles and client behavior. The second DC was considered complete only after it was proven able to participate in real authentication and policy services.

View project details →
Real-estate group in Hangzhou | JumpServer rollout for 80+ vSAN VMs and seven systems
HangzhouReal estate

Hangzhou real estate | JumpServer for 80+ vSAN VMs

JumpServer was introduced as a controlled operations entry point for more than 80 vSAN virtual machines supporting seven business systems. The delivery focused on assets, roles, accounts, authorization and phased cutover rather than treating bulk asset import as project completion.

View project details →
IC design company in Fengxian, Shanghai | Windows Server 2019 secondary DC and GPO replication
Shanghai FengxianIC design

Shanghai IC design | Windows Server 2019 secondary DC

A Windows Server 2019 secondary domain controller was added to an existing AD environment. Acceptance focused on directory replication, DNS, SYSVOL/NETLOGON, GPO consistency and real client authentication—not simply on the new server showing as a domain controller.

View project details →
Manufacturing company in Hangzhou | Phased redesign of a /23 flat network into office, production, server and guest zones
HangzhouManufacturing

Hangzhou manufacturing | /23 network segmentation

The original /23 network had grown to roughly 379 used addresses, with office, production and wireless access sharing the same boundary. The project kept the existing subnet as a migration anchor and introduced four controlled zones without forcing a big-bang production cutover.

View project →
Active Directory migration | Windows Server 2008 to 2016 while retaining the legacy file server
Single-domain environmentWindows Server

AD migration | Windows Server 2008 → 2016

AD DS, DNS, Global Catalog and FSMO roles were moved to a new Windows Server 2016 domain controller. The legacy server kept its existing SMB file-sharing role and address, while DHCP remained on the core switch. The migration was accepted only after directory, DNS, SYSVOL, logon and file access were verified together.

View project →
Manufacturer in Fuyang, Hangzhou | Backup validity review found three unusable jobs and moved acceptance to restore testing
Fuyang, HangzhouManufacturing

Fuyang manufacturing | Backup validation & restore testing

This was not a replacement backup deployment. The project reviewed the existing jobs, protected objects, storage location, retention and restore conditions, identified three unusable jobs, remediated them and re-established the backup baseline through a low-risk restore test.

View project →
Trading company in Linping, Hangzhou | Active Directory rebuild with cleanup of roughly five years of legacy file ACLs
Linping, HangzhouTrading

Linping trading | AD rebuild & legacy ACL cleanup

The customer needed to rebuild Active Directory while the file environment carried about five years of ACL history. Instead of clearing permissions in one step, the project mapped folders, users, groups and legacy grants, then rebuilt identity and file access in controlled stages.

View project →
Two-site business in Hangzhou and Jinhua | Two-site AD rebuild, domain trust and controlled file-sharing access
Hangzhou / JinhuaTwo-site operations

Hangzhou–Jinhua | Two-site AD & file access

The two sites were already connected through the existing firewalls, so the project did not reopen the underlying WAN design. It rebuilt AD and GPO at both locations, established domain trust, introduced a new file server and created controlled cross-site permissions.

View project →
Growing business | Infrastructure handover after IT staff transition and rebuild of the operating baseline
Enterprise environmentGrowing business

Growing business | Infrastructure handover & managed support

The handover did not begin by changing every password. Non-essential changes were frozen first, then directory services, virtualisation, network, NAS, backup, cloud accounts and ownership were inventoried before permissions, configuration backups, dependencies and restore checks were brought under control.

View project →