Project context
The new environment combined dual firewalls, core networking, Active Directory, backup and an internal VDI platform. Because each workstream depended on the others, the project established the overall topology, addressing, access paths and identity dependencies before installation, then brought the layers online in controlled stages.
Objectives
- Deliver the dual-firewall, core-network, AD, backup and internal VDI environment as one coordinated infrastructure program.
- Define subnets, access relationships, identity dependencies and critical traffic flows before implementation.
- Create validation gates and rollback points between workstreams so one change did not destabilize the next layer.
Scope baseline
Establish the topology, addressing and dependency baseline across all workstreams.
Stabilize network and security boundaries before identity and desktop services.
Pilot VDI with end-to-end authentication, DNS and application access checks.
Bring backup tasks into the final baseline and retain configuration/validation records.
Delivery and controls
- 01
Establish the topology, addressing and dependency baseline across all workstreams.
- 02
Stabilize network and security boundaries before identity and desktop services.
- 03
Pilot VDI with end-to-end authentication, DNS and application access checks.
- 04
Bring backup tasks into the final baseline and retain configuration/validation records.
- 05
Consolidate topology, addressing, firewall policy, identity, VDI and backup evidence into a single operational handover set.
Risk and change control
Network and firewall changes were staged to avoid introducing several routing or policy variables at once.
AD/DNS dependencies were validated before VDI enrollment and user testing.
Backup jobs and representative recovery checks were completed before the environment was treated as production-ready.
Acceptance and handover
- Core network, dual-firewall policy and critical business access paths were validated against the design.
- AD/DNS, VDI sign-in, domain authentication and internal application access worked as one end-to-end path.
- Critical backup jobs ran and representative recovery checks were completed.
- The project handed over topology, address/policy baselines, system inventory, validation evidence and maintenance notes.